WireWicket / NEC 314 · 2026 reference data
Box fill & pull-box sizing
Add each applicable fill allowance or check minimum pull-box dimensions. The calculation uses fixed NEC 2026 reference data; a project’s selected edition remains separate.
Within selected box volume
0.75 in³ remaining.
- Required volume
- 20.25 in³
- Selected box volume
- 21.00 in³
- Remaining volume
- 0.75 in³
Allowance breakdown
- 13.50 in³
Conductors and qualifying long loops 314.16(B)(1)
6 × 12 AWG at 2.25 in³
- 4.50 in³
Device yokes / straps 314.16(B)(4)
1 yoke(s) × 2 × 12 AWG allowance (2.25 in³)
- 2.25 in³
Equipment grounding / bonding conductors 314.16(B)(5)
1 conductor(s): 1 allowance for the first four + ¼ allowance for each additional conductor, based on 12 AWG (2.25 in³)
21.00 in³ listed volume (Table 314.16(A))
Box fill: 314.16(A), Table 314.16(A), 314.16(B)(1)–(6), and Table 314.16(B)(4). Pull boxes: 314.28(A)(1)–(2). A project’s selected NEC edition is shown as project context and does not change this fixed 2026 data set.
Reference aid only. Verify the edition adopted by the jurisdiction, local amendments, box listing and project conditions with the authority having jurisdiction. This calculation does not replace professional design or inspection.